![]() |
Reprocessing
and
Reuse of Street Waste Solids |
Table
of Contents
Executive
Summary 1
1. Introduction 4
1.1 Project Overview 4
1.2 Problem Statement 4
1.3 Reuse Alternatives 4
1.4 Proposed Solution 6
1.5 Project Objectives 6
1.6 Previous Studies 6
2. Street Waste Characterization 9
2.1 Preliminary Testing of Street Waste Solids 9
2.2 Conclusions 9
3. Separation
Alternatives 10
3.1 Introduction 10
3.2 Liquid Separation 10
3.3 Vibratory Separation 11
3.4 Air Separation 12
3.5 Mechanical Screening 13
3.6 Combustion 15
3.7 Component Equipment for Material Separation 15
3.7.1 Log Washer 15
3.7.2 Fine Material Screw Washer 16
3.7.3 Dairy Manure/Sand Separator 17
3.7.4 Vibratory Air Knife Separator 18
3.8 Further Discussion of Separation Alternatives 19
3.8.1 Mechanical Screening 19
3.8.2 Wet System Separation 20
3.8.3 Dry System Separation 21
3.8.4 Combustion 22
3.9 Conclusions 23
3.10 Recommendations 25
4. Economic Evaluation 27
4.1 Basis for Economic Evaluation 27
4.2 Discussion of Processing Costs 28
4.2.1 Existing Aggregate Wash
Plant and Concrete Batch Plant 28
4.2.2 Dedicated, Private Receiving
and Processing Site 29
4.2.3 Dedicated Generator
Processing Site 30
4.2.4 Mobile, Private Processing
Equipment 32
4.2.5 Existing Asphalt Plant to
Burn Organics and Hydrocarbons 32
4.3 Conclusions 32
5. Full Scale
Materials Separation Test 34
5.1 Overview 34
5.2 Pre-Screening 35
5.3 Screen and Wash Separation Process 35
5.4 Soil and Water Sampling 37
5.5 Observations and Conclusions 38
6. Full Scale
Test - Analytical Test Results 40
6.1 Soil Samples 40
6.2 Water Samples 41
6.3 Conclusions 42
7. Summary of Conclusions 43
7.1 Previous Studies 43
7.2 Street Waste Characterization 43
7.3 Separation Alternatives 44
7.4 Economic Evaluation 45
7.5 Full Scale Materials Separation Test 46
7.6 Full Scale Test - Analytical Test Results 47
8. Acknowledgments 48
List of Tables
Table 1 - Existing Aggregate Wash Plant, Tip Fee
Estimates
Table 2 - Dedicated, Private Receiving and
Processing Site, Tip Fee Estimates
Table 3 - Dedicated Generator Processing Site, New
and Used Equipment Prices Table 4
Table 4 - Dedicated Generator Processing Site,
Operating Cost Estimates
Table 5 - Mobile, Private Processing Cost Estimates
Table 6 - Summary Cost Estimates
Table 7 - Estimated Proportion of Separated
Materials
Table 8 - Soil Sample Description
Table 9 - Water Sample Description
Table 10 - Summary Cost Estimates
Appendices
Appendix A - Snohomish
Health District Policy Statement Regarding Street Waste Solids Recycling and Disposal.
Appendix B - Summary and
Conclusions (Section 5) and the List of References
(Section 6), from Snohomish County Street
Waste Characterization (Landau
Associates, December 1995).
Appendix
C - Snohomish County Public Works, Road Maintenance Division, Laboratory Test
Results and Sweepings Testing Interim Report.
Appendix
D - Eco-Block Manufacturing as an Alternative Catch Basin Waste Disposal
Method, Kitsap County Public Works, Surface and Stormwater Management
Program, November 13, 1996
Appendix E - General
Kinematics Conceptual Drawing of Prototype Street Solids Separation Equipment, “Vibratory Air
Knife Separator”.
Appendix F - Land
Technologies, Inc. Schematic Drawing of Prototype Street Solids Separation Equipment.
Executive Summary
In 1993, the Washington State Department of Ecology
(Ecology) defined street sweepings and vactor grit as municipal solid
wastes. This action has resulted in
severe economic impact on public jurisdictions responsible for collection and
disposal of these materials.
Solids collected during the cleaning of storm
sewers, streets and drainage ditches (collectively referred to as “Street Waste
Solids”) fall into the state definition of solid waste established under RCW
70.95.030. Street Waste Solids typically
fail Model Toxics Control Act standards for total petroleum hydrocarbon
levels. A significant problem in
determining the contaminant concentrations of the street waste solids is the
presence of vegetative matter, which causes false positive analytical test
results. As such, both public and
private generators of these materials are disposing of this material in
landfills at considerable expense to the tax payer and private industry.
The Snohomish Health District (SHD), in accordance
with the Department of Ecology’s waste reduction and recycling objectives, is
promoting recycling options for street waste solids which protect both public
health and the environment. In January
1995, the SHD issued a Policy Statement Regarding Street Waste Solids Recycling
and Disposal (Policy), in which they define classes of materials, and reuse
options for each class. The Policy states that all potential end uses “would
first require the removal of litter and vegetative matter”.
The solution to this significant waste disposal /
resource utilization problem is to economically process these materials to
remove contaminating litter and organics, and to separate the mineral
constituents into specified size fractions (i.e., fine sand, coarse sand and
gravel) to produce useable and/or marketable end products. The solution also includes selecting a
processing technology that is economical and environmentally compatible for
this approach to be viable.
This report discusses five alternative methods of
material separation, including liquid, vibratory, and air separation,
mechanical screening, and combustion.
Considering the available technologies, five
alternative approaches for separating and utilizing the street waste solids are
recommended. These are discussed in
their order of preference.
The first recommendation is to haul street wastes to
existing aggregate wash plants equipped with wood removal equipment, and blend
these materials with daily process materials for use as aggregate in concrete.
The second is to seek an interested party (public or
private) to develop a dedicated processing site for the street waste
solids. The separation process may be a
closed wash system for all the street waste or a dry system with facilities to
condition the vactor waste before processing.
The third alternative would be for individual
generators to purchase equipment to process street waste for re-use at their
facility.
The fourth would be to seek an interested party to
develop a mobile processing plant. This
option would reduce handling and hauling costs and leave sand and aggregate
products for re-use by the waste generator.
The waste generator would also be responsible for disposal of unsuitable
materials.
The fifth and final option would be to haul the
street waste solids to an asphalt plant retro-fitted to burn organics and
hydrocarbons.
For the five alternatives
considered in the economic evaluation, the range of costs to process the street
waste solids materials are summarized in the following table.
Alternative
Description
|
Low cost/ton |
High cost/ton |
|
Existing Aggregate Wash Plant and Concrete Batch
Plant |
$5 |
$45 |
|
Dedicated, Private Receiving and Processing Site |
25 |
60 |
|
Dedicated Generator Processing Site |
17 |
25 |
|
Mobile, Private Processing Equipment |
25 |
50 |
|
Existing Asphalt Plant to Burn Organics and
Hydrocarbons |
45 |
75 |
A full scale separation test was conducted at the
Smokey Point Concrete plant in Arlington, Washington. This test successfully demonstrated that organics and fines can
be effectively removed from the mineral sand and gravel fraction.
The breakdown of the constituents were visually
estimated as follows:
Plus 1-inch 10
percent of total pile.
Of the remaining 90 percent that passed the 1”
screen:
1 to 5/8-inch 10
percent
5/8 to ¼-inch 15
percent
Coarse Sand 35
percent
Fine Sand 35
percent
Organics (sticks, pine needles & leaves) and
Silt 5 percent
Because of the heavy load of organics in the street
solids materials, it would be more effective to combine these materials with
other source materials prior to screening and washing. In this way, the percentage of organics
would be reduced in the process materials, and the efficiency of the total
system would be increased.
The concentrations of heavy oil in the soil samples
ranged from 230 ppm to 380 ppm, which characterizes this material as a Class B
soil, in accordance with the SHD Policy.
Concentrations of diesel in all liquid samples were well below
reportable levels.
1. Introduction
1.1 Project Overview
In 1993, the Washington State Department of Ecology
(Ecology) defined street sweepings and vactor grit as municipal solid
wastes. This action has resulted in
severe economic impact on public jurisdictions responsible for collection and
disposal of these materials.
1.2 Problem Statement
Solids collected during the cleaning of storm
sewers, streets and drainage ditches (collectively referred to as “Street Waste
Solids”) fall into the state definition of solid waste established under RCW
70.95.030. Street Waste Solids
typically fail Model Toxics Control Act (MTCA) standards for total petroleum
hydrocarbon levels. A significant
problem in determining the contaminant concentrations of the street waste
solids is the presence of vegetative matter, which causes false positive analytical
test results. As such, both public and
private generators of these materials are disposing of this material in
landfills at considerable expense to the tax payer and private industry. The cost for landfill disposal of Snohomish
County street sweepings and vactor grit waste is $89 per ton. As of January 1996, Snohomish County had
accumulated an estimated 1,600 cubic yards (~2,500 tons) of street sweepings,
representing a total potential liability of $222,500. In addition to street sweepings, the cost for disposal of vactor
grit exceeded $66,500 in 1995.
1.3 Reuse Alternatives
The Snohomish Health District (SHD), in accordance
with the Department of Ecology’s waste reduction and recycling objectives, is
promoting recycling options for street waste solids which protect both public
health and the environment. In January
1995, the SHD issued a Policy Statement Regarding Street Waste Solids Recycling
and Disposal (Policy), presented as Appendix A.
In the Policy, Street Waste Solids are divided into
two categories, including Class A and Class B materials, which are determined
by maximum contaminant levels. The two
material classes have identified potential end uses, including:
Class A
·
Encapsulated
soil fills and pipe bedding which are not likely to result in contamination of
ground or surface water or lead to other potential environmental or public
health problems.
·
Reuse
as street traction sand.
Class B
·
Pre-fabricated
concrete manufacturing, Portland cement manufacturing and asphalt
manufacturing, provided a recycling permit application is submitted and
approved by the SHD.
·
Treatment
at a contaminated soil treatment facility.
·
Daily
cover of fill in a permitted municipal solid waste landfill.
The Policy states that all potential end uses “would
first require the removal of litter and vegetative matter”. In addition, “all recycling end-uses must be
conducted in compliance with specifications required by federal, state or local
regulations, or specifications required by a facility, manufacturer or vendor
accepting the street solids for processing or recycling”.
1.4 Proposed Solution
The solution to this significant waste disposal /
resource utilization problem is to economically process these materials to
remove contaminating litter and organics, and to separate the mineral
constituents into specified size fractions (i.e., fine sand, coarse sand and
gravel) to produce useable and/or marketable end products. The solution also includes selecting a
processing technology that is economical and environmentally compatible, for
this approach to be viable. As part of
the solution, a sampling and laboratory testing program was implemented to
establish whether the processed materials meet the SHD’s Class A or Class B
criteria.
1.5 Project Objectives
The objectives of this project were three-fold:
·
Evaluate
existing, cost effective technologies for physically separating street
sweepings and vactor grit constituents (sand and gravel, from organics, silt,
and litter);
·
Determine
the level of contamination of the separated mineral fraction, with regard to
the SHD reuse criteria; and
·
Evaluate
viable reuse alternatives for the sand and gravel components which contribute
to protection of human health and the environment, and reduce landfill
quantities and costs.
1.6 Previous Studies
Numerous studies have been completed by Ecology and
local municipalities to evaluate the character of street waste solids, and to
develop analytical methods for resolving the problems associated with false
positive laboratory test results.
Of these studies, the most recent was conducted by
Landau Associates, Inc. for Snohomish County and the City of Everett. The final report for this study, entitled Snohomish
County Street Waste Characterization (December 1995), provides the following
conclusions:
·
Organic
(plant) material contributed to a false positive result with each of the three
total petroleum hydrocarbon (TPH) analysis methods used;
·
Sources
likely to contribute to TPH concentrations in street waste include organic
(plant) material, automobile and truck tires, asphalt paving materials, and
motor oil and lubricants from cars and trucks.
Relative amounts of contribution to the TPH concentration were not
identified.
·
Street
waste is a solid waste and is typically not a dangerous waste, and Ecology and
the SHD regulations support reuse of street waste.
·
Chemical
analysis results for metals do not exceed MTCA Method A soil cleanup levels or
SHD threshold criteria, and do not limit reuse options.
·
Chemical
test results for CPAH exceed SHD threshold criteria and may limit management
options to those associated with Class B material.
The Summary and Conclusions (Section 5) and the List
of References (Section 6) from the Landau Associates report are presented as
Appendix B.
Prior to this project, samples of street sweepings
and vactor grit were tested by Snohomish County to determine the presence of
contaminants and classify material for reuse.
Handling, storage and processing evaluations were done to classify the
street sweepings using the criteria in the SHD Policy. Six samples were evaluated for gradation by
sieve analysis and twenty three samples were selected for analytical
testing. In all cases, the test results
indicated that total metals, PAH’s, PCB’s and BTEX were below detection
limits. TPH results showed
concentrations from 85 - 620 parts per million, after silica gel and acid
cleanup step on the extracts. Summary
tables of these test results are presented in Appendix C.
Vactor grit land use classification study of 15
locations defined a baseline for classification using the TPH 418.1 test,
however that test has subsequently been replaced with the TPHDx with cleanup,
due to the false positives in samples from organics. ICP metals tests were run on these samples for the seven basic
reference metals with only two of the 115 analytical results exceeding the
acceptable Petroleum Contaminated Soils (PCS) threshold. No PAH results exceeded the thresholds.
The WTPH-D extended method with Silica Gel and Acid
Wash modification, per Washington Ecology Laboratory, is the current preferred
method for testing street wastes.
Multiple test sample results have substantiated that this procedure
eliminated about 85 percent of the false positives caused by organics in the
samples.
Three other prototype tests have been evaluated by
Snohomish County Road Maintenance using screened and tested street sweepings.
1.
Composting
of high organic content material is currently being evaluated.
2.
Use
of street sweeping solids for top dressing on reclamation slopes, as described
in the Snohomish County Public Works Road Maintenance Division Sweepings
Testing Interim Report, presented as Appendix C.
3.
Encapsulation
of material in precast concrete products, even with fine organics achieves
satisfactory results. Eco-Block
manufacturing by Kitsap County Public Works has been successful, as discussed
in a paper by this title, presented in
Appendix D.
2. Street Waste
Characterization
2.1 Preliminary Testing of Street Waste
Solids
At the outset of this project, preliminary
laboratory tests were conducted on one composite sample of dry street sweeping
material. The sample was first screened
into size fractions using US Standard sieves, and then each size range was further
separated into mineral and organic fractions using a vacuum line to pull off
the lighter organic materials. The
organic material (Sample SS-9 in Table 1) showed values for heavy oil that
exceeded the reportable level. These
results may in part be indicative of the false positives derived when testing
organic materials.
Of the mineral components, the initial acid clean-up
test results also showed that the 3/8-inch plus fraction (Sample SS-10)
slightly exceeded the heavy oil limit while the fine sand (Sample SS-11) was
under the reportable level. Retesting
of the 3/8-inch fraction (Sample SS-10A) showed that this material was also
under the reportable level.
2.2 Conclusions
Given these preliminary test results, the separated
mineral fraction could be used for any of the Class A and Class B applications. In the event that future samples showed
heavy oil concentrations exceeding the 200 ppm criteria, then these materials
would be restricted to Class B reuse alternatives.
3. Separation Alternatives
3.1 Introduction
There are a wide array of material separation and
handling technologies available in heavy industry for processing highly
variable solid materials. Street waste solids consist of comparatively dry
street sweepings and wet vactor grit, each with seasonally variable quantities
of organics. Separation of these highly
variable waste materials could be accomplished by a combination of mechanical
separation by size and density with effective use of a liquid (water),
vibration, air flow, and mechanical screening.
Another method of separation is by use of heat, which generally causes a
conversion of at least one of the components. In practice, combinations of the
above technologies are often used to process and separate common waste
products. Each of these basic methods,
along with the several specific technologies, are discussed in the following
sections.
3.2 Liquid Separation
Historically, liquid separation was the first method
commonly used for separating combined materials where individual components
have varying particle density. Natural
geologic processes demonstrate the power and effectiveness of liquid
separation. For example, in a marine
environment, where water motion often ranges from highly turbulent to
quiescent, a well graded mix of materials can be effectively separated into the
separate constituents, including boulders, cobbles, gravel, sand, silt and clay
materials that settle, and organics which float.
Numerous mechanical systems have been developed that
perform the same function as natural liquid separation processes to separate a
wide range of materials. For example,
water has been used in numerous types of float tanks designed to separate rock
used in log handling operations from bark and wood that falls off the logs and
intermixes with the rock. By theory,
the rock will sink to the bottom of the tank and the wood should float off the
top. Complications arise when saturated
wood sinks along with the rock. Various
methods have been devised to increase the “floatability” of the wood, usually
by use of upstream currents or jets.
These “float tanks” work well when the wood is dry and floatable.
3.3 Vibratory Separation
Material on a vibrating conveyor is said to be
“alive” and moves independently of the conveying medium, unlike other types of
conveyors where the material is static and the conveying medium moves. This characteristic provides a solution to
many difficult materials handling and processing applications with highly
varied materials, including street waste solids.
The separation equipment can provide a range of
motion, from an aggressive tossing action to a gentle sliding motion. This range is determined by the adjustable
combination of amplitude, total movement of the material carrying deck,
frequency, and the number of cycles of motion for a given time period, together
with the angle at which the resulting force is applied.
In addition to conveying materials, the vibratory
action has the effect of stratifying the materials into layers, wherein the
materials with greater density “sift” to the bottom and the lighter density
materials “float” to the top. To a
lesser degree, the vibratory action also sorts by size, wherein two materials
with roughly the same density will sort out with the finer material beneath the
coarser.
Vibratory conveyance and sorting systems are often
used in conjunction with air separation systems. Common in agriculture, is the use of slanted vibratory
tables. The particles will stratify
horizontally, a mechanical split can be made along the light/heavy line sending
each classification a different direction.
More effective is to use an airstream to blow away the lighter fraction
after it has been separated from the bulk of the heavier fraction.
3.4
Air Separation
Air separation systems take advantage of differences
in material density, particle size and aerodynamic characteristics to separate
mixed materials into component parts.
For example, it would be an easy matter to separate lead shot from
feathers using a stream of air.
Similarly, rock, sand and wood can also be separated because each
component responds differently to a stream of high pressure air.
A steady stream of air, combined with vibration, has
been used to stratify the material in preparation for separation. This is often followed by a high pressure,
linear stream of air from a device known commonly as an air knife. This type of vibrating / pneumatic
classification equipment is used extensively in waste recovery industries to
process various materials including bio-mass fuels, auto shredder fluff,
construction/demolition waste, scrap processing and tire recycling.
The above described air separation equipment is very
specialized and is generally used on materials with a size range varying from ½
inch to 8 inches. Cyclones are commonly
used in gas/solid separation of small “dust” like particles from an air
stream. Basically, a particulate-laden
air stream is mechanically forced into a cone shaped cylinder, specifically
designed for each type of gas/solid mixture, the airstream forms a high
velocity vortex and centrifugal force hurls the denser particles toward the
cyclone walls. The denser particles spiral downward into a collection
receptacle and the lighter fraction, generally the gas, is exhausted from the
cyclone’s outlet. A properly
designed cyclone can remove up to 99.9%
of the solids from an air stream.
Cyclones can be used in sets and designed to separate multiple particles
in a gas stream by density and size before exhausting a clean gas stream.
3.5 Mechanical Screening
Mechanical screening is another common method of
classifying materials, primarily by size.
Screening systems rely on gravity for the flow of material, and can
consist of single screens or sets of multiple screens with varying opening
sizes. In all cases, coarser material
is retained on the screen as finer material passes through the screen. The separated material typically exits the
screen at different points and is conveyed away from the equipment for separate
discharge and handling.
There are numerous types and configurations of screens,
with the three predominant types being the vibratory deck screen, the trommel
screen, and the disc screen. The
vibratory deck screen typically consists of a feed hopper that meters the
material onto a conveyor that in turn feeds a uniform stream of material onto
the vibrating set of screens. The feed
hopper is commonly equipped with a “grizzly” or multiple set of parallel bars
designed to separate the very large material.
A vibratory deck screen commonly separates materials into three or four
size components.
Vibrating deck screens that use “cascading fingers”
are somewhat more effective than a grid screen but still will not remove
adhered fines effectively nor will they break up agglomerated particles. The fingers will collect organic strings at
the ends of the runs and need to be shut down and cleaned periodically as these
strings build up. This cleaning has to
be done by hand and the shut down stops production
A trommel screen consists of a gently sloping,
cylindrical screen that rotates. The
material is fed into the trommel screen using a metering feed hopper and
conveyor, similar to that of the vibratory deck screen. As the material is tossed across the screen
surface, the fines pass through onto a return conveyor for side discharge, and
the coarse materials (“overs”) exit the end of the screen. Some trommels have two screen sizes, with
the larger screen located near the discharge end. In this case, the two screened materials are generally allowed to
fall into separate bins beneath the screen for removal using a front end
loader.
The trommel is probably the most effective piece of
screening equipment that can process and condition wet material for further
separation. With lifting flights installed in the screen, material will be
lifted, turned and dropped onto the effective screen surface, breaking
agglomerated chunks and jarring free adhered particles. Chains have been installed in the screening
chamber to further breakup and break free agglomerated and adhered particles
into free particulates for clean size separation. The trommel slope can be easily adjusted so as to increase
retention and exposure to the screen surface, thus cleaning the oversize waste
material. The trommel is the
recommended sizing and preconditioning screen for use with the street solids,
especially vactor waste.
Disc screens, or “star” screens, are also effective
for separating organic laden and somewhat cohesive materials. Rapidly rotating discs lift and drop
materials with an aggressive rolling action that breaks up cemented or adhered
materials. This violent action exposes
more surface to the screening aspect, and since every disc is rotating, it is
self cleaning.
The primary disadvantage with the vibratory deck
screen is a tendency for the screen decks to clog up, or blind, with fine and
damp material that adheres to the screen.
Several attempts have been made to equip these screens with a
self-cleaning mechanism, but short of stopping the process and brushing the
screen clean, none have worked with organic or cohesive materials. The flat
deck vibratory screen is not very effective on materials with a high organic
content or on particles that have high cohesiveness.
This problem is somewhat overcome with the trommel
screen. As a rotating cylinder, brushes can be placed on the high side of the
screen and the brushes rotate as the trommel rotates. The bristles penetrate
the screen openings and remove the fines thereby maintaining the full
screen-opening dimension as it passes under the material in the effective
screen area.
The disk screen is commonly used in the waste
industry, as it has better production rates than a trommel. The oversize, which is usually the waste, is
cleaner with little lost “product”. The star screen is usually equipped with
polyurethane discs that would be subject to excessive wear with the aggregate
materials. The star screen is very
effective with organic materials where the medium is not as abrasive. The disc screen is not as simple
mechanically as the trommel, therefore maintenance can be considerably higher.
3.6 Combustion
When components of a mixed particle stream have
different combustion temperatures, with the desired “product” having the
highest, the undesired product can be burnt off leaving the desired
product. Specific to the street waste
material, both the undesired hydrocarbons and the organics can be vaporized,
leaving a relatively clean aggregate material.
Several asphalt plants have retrofitted their plants
to receive hydrocarbon laden materials.
With the street wastes, this type of processing could fit, since the
aggregate product left after processing is ready for use in asphalt. The limiting factor with this separation
process is the cost. Facilities
actively receiving this type of material are charging about $40 to $50 per
ton. In addition, the hot embers from
the organic fraction have been reported to cause problems with the bag houses
which are susceptible to fire.
3.7 Component Equipment for Material
Separation
3.7.1 Log Washer
A log washer is a liquid separation device that
operates with sets of rotating paddles mounted on a shaft, combined with
high-pressure water jets. The name of
this equipment is a carry over from late nineteenth century practices when
paddles were affixed to logs that rotated, thereby causing the desired
agitation of the water and materials to be separated. The technology has advanced significantly since the turn of the
century, and is used widely for washing gravel, cemented aggregates, limestone,
phosphate and various ores.
Nevertheless, the shaft to which the paddles are bolted is still
referred to as “the log”.
Log washers commonly provide from 80 to 125 tons per
hour capacity when washing average natural gravel up to 4-inches in size. Capacities are reduced for washing material
that is crushed or angular since this material does not move as freely as round
or natural aggregate. In general, the
capacity also varies with the percent and tenacity of fines to be removed.
Log washers range in size from small units measuring
36-inches by 25-feet to larger units measuring 46-inches by 35-feet. Water requirements range from 75 to 150
gallons per minute (gpm) for the smaller units up to 300 gpm for the larger
units. In all cases, the water jet
pressure is on the order of 75 pounds per square inch (psi). Horsepower (HP) requirements range from 60
to 75 HP for the smaller units up to 150 to 200 HP for the larger units.
3.7.2 Fine Material Screw Washer
A screw washer consists of a gently sloping,
continuous helical screw, partially submerged in an elongated tank, or “washer
box”. A feed hopper is located at the
low end of the device and receives a liquid slurry of silty and fine granular
material. This method of separation
relies on low energy ( i.e., minimal turbulence) to allow the mineral fraction
to settle to the bottom of the washer box.
The curvature of the rotating screw flights conforms to the curved
section of the washer box to efficiently convey, wash the sand particles, and
direct the water away from the sand to the opposite side of the washer box
where a drainage channel is designed for quick removal of water from the dry
deck area.
Water manifolds and adjusting weirs in the large
pool area at the feed end of the screw washer enable the operator to adjust the
amount of fine sand required in the end product. The classification of fines in this manner may be sufficient to
meet product specifications without prior classification in a sand classifying
tank.
The principal working component of the fine material
screw washer is an extra heavy steel pipe shaft with continuous spiral steel
screw flights welded to the pipe shaft.
The flights are typically equipped with renewable, wear-resistant
polyurethane shoes. At the drive end, a
flange on the screw shaft is bolted to a mating flange on the stub shaft. The screw shaft at the feed end is attached
to the submerged bearing shaft. These
flanges permit easy removal of the entire screw from the washer box.
Screw washers come in single and double screw
configuration. A single screw model
ranges in size from 36-inches by 24-feet up to 72-inches by 36-feet. The double screw ranges from 36-inches by
24-feet, to 72-inches by 38-feet. The
capacity of this equipment ranges from 35 to 475 tons per hour (tph) for the
single screw washer and 210 to 950 tph for the double screw washer. Horsepower requirements range from 5 to 75
HP for the single screw and from 2 times 15 HP to 2 times 75 HP for the double
screw.
3.7.3 Dairy Manure/Sand Separator
The McLanahan Sand/Manure Separator removes bedding
sand from dairy manure prior to long term storage of the manure fraction. Sand
/ manure separation is a liquid (manure slurry) based process that relies on
turbulent water action to “flush” the organic materials out of the sand matrix,
and allow the clean sand to be removed from the apparatus with a screw
conveyor. Dilution water is used with
this system, however the water is recycled.
The amount of organic manure solids remaining in the recovered sand is
reported to be minimal, and the manure fraction contains a minute amount of
only the finest sand particles.
This separation technology is new, with the first of
the full scale proto-type models only recently installed at a large dairy in
Michigan. While there are bench scale
models available for testing, there is no long term operational experience with
the full scale equipment.
McLanahan Corporation, of Holidaysburg,
Pennsylvania, was provided samples of both the Snohomish County street sweeping
solids and the vactor grit for bench scale testing. Based on preliminary sieve analyses, they felt that the sand
separation equipment would work for the intended purpose, however not as well
as their fine material screw separation equipment. For this reason, the sand / manure separator was dropped from
further consideration.
3.7. 4 Vibratory Air Knife Separator
General Kinematics (GK), of Barrington, Illinois has
prepared a design for a prototype separation device, specifically intended to
separate street sweeping and vactor grit materials. This device, with the working name “Vibratory Air Knife
Separator”, combines mechanical screening, vibratory and air separation
technologies from their other existing classification equipment. GK plans to construct the prototype in 1997
to 1998, and conduct extensive full scale field tests for municipalities
throughout the northwest United States and western Canada. A copy of the GK preliminary design drawing
is presented in Appendix E.
The flow of materials with this equipment would
include screening and removal of the coarse materials, air and vibratory
stratification and air knife separation.
Being a dry system, dust and litter control would consist of a cyclone
and possibly a small bag house device.
Depending on the flow through requirements, the equipment may be small
and portable for mobile operations or larger for stationary centralized
operations.
Product specifications, including size, weight,
capacity, motor horsepower, etc. are not available at this time.
3.8 Further Discussion of Separation
Alternatives.
Street waste solids consist of both wet and dry
materials, made up of several
components varying in size, density and combustion temperatures. With these characteristics, several
alternatives are available to process this waste into viable products
acceptable for reuse by the regulating agencies. Three categories of separation are feasible for this material 1)
a wet separation using water, 2) dry separation using an air stream combined with
vibration, and 3) combustion. Each of
these alternatives will use mechanical screening to remove litter and oversized
material as a precursor to further separation by other physical
characteristics, and therefore screening alternatives are evaluated with these
other choices.
3.8.1 Mechanical Screening
Street waste solids come in two primary states; one
is as a primarily dry material from street sweepings and the other is as a
generally very wet vactor waste which has been wet vacuumed from catch
basins. The dry street sweepings can be
screened effectively over any industrial screening equipment, however, the wet
vactor waste can only be effectively separated using a trommel or disc screen,
each of which has the means of
de-blinding itself. Using either of
these methods, the oversize material will still have a relatively small
percentage of fines or product mixed with it.
The off-size material is the waste material that may have to be hauled
to a landfill. Economically, it is
important to clean this waste material as effectively as possible.
3.8.2 Wet System Separation
Wet separation in western Washington is an
attractive process alternative. While
the street sweepings can be easily dry separated, the vactor waste would need
extensive pre-conditioning. Wet
separation eliminates the need to dry the vactor waste. Use of the water medium does have a water
quality aspect that needs to be addressed.
Physical separation by use of water is effective in yielding good
quality products of sand and rock.
Several commercial concrete plants have existing equipment that can be
used in their everyday processing to produce aggregate that meets industry
specification for concrete products. A
full scale test was done at Smokey Point Concrete, in north Snohomish County,
and is described in Section 5 of this report.
This test demonstrated that four suitable aggregates could be produced
for use in concrete, including fine sand, coarse sand, pea gravel, and a #5
rock.
The downfall of a wet system separation system is
the water required. Significant volumes
of water are used in any flow through wash system. Static float tanks require less water but are not very effective
in washing the product clean. A “live
system” (using flowing water) would use at least 50 gallons a minute for the
smaller system and up to 200 gallons per minute for larger systems. Recycling of the water with some makeup
(replacement water) supply is most reasonable.
Several clarifying systems have been used in the waste industry and the
aggregate industry. Most water
recycling systems deal primarily with solids in water, and utilize clarifying
tanks for removal of sediment prior to reuse of the water. These systems are used by the aggregate
industry at sites that have a limited water source. Clarifying tanks have a low volume of water when compared to
lagoon type systems, and with the large rate of use these systems need polymers
to help settle out solids. The polymers
leave the system with the silts that are usually drag-chained from the bottom
of the clarifying tank. An additional
requirement of this type of water clarification, specific to street waste, may
be a treatment system for removal of hydrocarbons from the wash water.
3.8.3 Dry System Separation
The great advantage of separating materials with an
air stream is not having to contend with the wash water. The disadvantage is the need to dry the
vactor waste before processing. In most
cases, this would mean stockpiling until the summer sun could be used to
adequately dry the material or stockpiling out of the weather until the
material is dry. The vactor waste could
be dried with forced heat through a pile (undercover) or in a rotary
drier. This would eliminate the storage
aspect, but would increase the processing cost significantly (however it would
still be significantly cheaper than disposal at a landfill).
Unlike the wet separation process, there is no
ready-made equipment that can be bought off the shelf to set-up a dry
separation system. A system would have
to be specifically designed for the street waste material. Land Technologies, Inc. of Arlington,
Washington has previously designed and built a prototype air separation system
that was used to separate log yard debris, a waste stream that is far more
difficult to handle than the street waste. The design included a vibratory
screen for preliminary material segregation and a cyclone to further separate
the fines from the air stream. This
prototype design would be very effective for street wastes. A schematic of this equipment is presented
in Appendix F.
General Kinematics makes several air separators
called “de-stoners” that are used in the waste recovery industry, and are
currently working on the design of a system that could be used for dry street
wastes. This system uses vibratory
screen and air knife to separate the light fraction from the heavier fraction.
A cyclone would have to be added to this system, for fine material recovery and
air quality (dust) control.
A dry separation system could be made the most
portable and versatile of all the options available; it would be the least
expensive of the options when building a new system specific to street waste
separation. For municipalities or
private companies that wanted to process their own waste materials, dry system
separation equipment would be the best choice.
The product produced by the air separation process
would not be as finished as the wash system, but would be a good usable
aggregate. The product out of the air system would be a clean pit run
gravel. Screening could produce sand
for re-use on the roads and an un-washed rock aggregate. The organic fraction would not be “lost” to
the process and could be used in compost or soil mixes. These uses would be conditioned on the
levels of total petroleum hydrocarbons found in each of the components, in
accordance with the Snohomish Health District Policy (refer to Section 2).
3.8.4 Combustion
Combustion removes some of the residual problems
left by the other options discussed, namely, the hydrocarbons are volatilized
and are not re-circulated back into the environment. Except for ash residue, the organic fraction is removed, leaving
only the aggregate which, if prescreened to the specified size, could be used
directly in asphalt. Several asphalt
producers have fitted their plants so as to be able to receive hydrocarbon
contaminated soils. In addition,
special precautions would need to be taken to avoid fire resulting from hot
embers produced by the burned organic materials.
Asphalt generally uses a ¾ inch minus stone and for
the Class B specifications, that is usually a 5/8 inch fractured rock. The street waste aggregate would be used in
Asphalt Treated Base (ATB), which is a lower quality asphalt, usually placed in
4 inch lifts under a Class B wearing course.
If a one-inch aggregate is not acceptable, this process would generate
more waste material for disposal.
Two options are viable with combustion: 1) process
the whole waste fraction through the burner, and 2) Prescreen and deliver only
the asphalt usable fraction to the burner for direct use in ATB. The first option is a one-stop means of
disposing of all the street waste with little extra handling. The results would be a clean bank run gravel
that could be used in any application currently used for gravel, and could be
processed with any end use goal. There
may be fewer options as to who could accept and process the “raw” street
wastes, and therefore hauling costs and tipping fees would be higher.
The second option, that of prescreening to meet an
ATB aggregate size specification, would increase the number of asphalt plants
that could accept and use the material.
Prescreened, the street waste could be used directly. Perhaps it could be blended with other
aggregate, in the production of ATB.
With direct use, the asphalt producer could charge a smaller tipping
fee. Prescreening to ¾ inch would leave
more waste requiring disposal.
3.9 Conclusions
For generators of street waste solids, the easiest
option to implement would be to haul the street wastes to an existing facility
that could utilized the aggregate fraction of this waste. Alternatives would
consist of either a concrete plant that has equipment in line for removing wood
contaminants from the aggregate, or an asphalt plant retrofitted to burn
hydrocarbon soil.
A concrete plant could be the least expensive option
if the street waste, after pre-screening, could be blended into their regular
bank run aggregate prior to processing through the wash plant. This would cause little disruption in the
daily process and would provide another source of aggregate for the concrete
producer. If the generator prescreened
the street wastes so there was no waste handling required of the concrete
plant, tipping fees would be minimal.
If the street wastes could not be pre-screened by the generator, tipping
fees would have to cover screening and waste disposal. While this approach is technically
desirable, special approvals would need to be obtained from the jurisdictional
Health District to mix street waste solids with regular bank run material.
If regulating agencies would not approve the
blending of materials at an existing wash plant, and a dedicated process had to
be implemented, cost would increase dramatically. Nevertheless, the cost of processing would still be considerably
less than landfilling. If a concrete
plant was willing to retrofit their process to process the street waste as a
dedicated operation, it would still be viable and the preferred option. Wash water quality would still be the
primary issue that would limit the concrete plant’s ability to handle the
material, and a water treatment process would likely have to be incorporated
upstream of the point of discharge to the water supply pond.
There are several resource recovery yards that
currently handle CDL (Construction, Demolition and Land Clearing debris)
waste. One of these sites could set up
a dedicated separation process using a closed wet separation system or an air
separator. As mentioned earlier, the
wet system would produce the highest quality end product, but has a water
quality issue that would need resolution.
The air separator means pre-conditioning (drying) the vactor waste
before separation. If storage space is
not a problem, this could be done by waiting for dry weather and then “land
farming” the material to dry and precondition the material before
processing. Street sweepings are
generally dry enough to air separate without further drying, especially during
the summer.
Development of a portable system that could go the
generator’s stockpiles would be a desirable solution. To accomplish this, enough generators would need to cooperate on
a long term contract basis, either through an interlocal agreement or with
private industry, to provide enough revenue to capitalize and operate a system.
A portable air separation system would eliminate the
water quality issues associated with wet separation systems and would be the
easiest to design and build for portability.
Generators could consider an air separation system for recovery of sand
from their street sweepings. For onsite
application, this option would be the least costly. In all cases, the vactor waste would need drying prior to
processing by air.
With street
sweepings only to consider, air separation is the most viable solution to
recovery and reuse. When vactor waste
is included, more complexity develops.
At issue is the water in the vactor waste and its cost of removal,
either by active dewatering and the use of energy, or by passive dewatering and
the cost of storage until dry weather farming can condition the waste to air
separation.
Alternatively, to facilitate processing the vactor
waste materials, the 3/8-inch minus material could be mechanically screened,
and the sand fraction could be cleaned and further separated using a fine
material sand screw. This would process
approximately 65 to 70 percent of the total volume of vactor waste. The remaining material, without the fine
fraction, would dry relatively quickly under cover or in dry weather, and could
then be further processed using a selected dry separation technology.
Combustion is a solution that is currently available
at about one half the cost of land filling. If water quality issues prevent
washing the street waste at a concrete plant, the vactor waste could be
processed at an asphalt plant and the street sweepings could be air
separated.
3.10 Recommendations
Several viable recommendations for processing street
wastes are discussed below, in order of preference.
The first recommendation is to haul street wastes to
existing aggregate wash plants equipped with wood removal equipment, and to
blend these materials with daily process materials for use as aggregate in
concrete. To accomplish this, it would
be necessary to resolve regulatory issues with the Jurisdictional Health Districts
and Ecology regarding: 1) blending street waste solids with bank run materials
to facilitate separation, and 2) wash water quality.
Second, seek an interested party to develop a
dedicated processing site for the street waste solids. The separation process may be a closed wash
system for all the street waste or a dry system with facilities to condition
the vactor waste before processing.
A centralized processing facility could be set up at
one of the sites currently permitted to take construction and land clearing
debris. To warrant the capitalization
expense, multiple generators would have to contract with possible a receiver as
no single source has enough material to create a large enough income stream.
Third, individual generators could purchase
equipment to process street waste for re-use at their facility. Because of the relatively small quantities
produced by each jurisdiction, small production rates would be acceptable and
therefore small, less expensive equipment would be required. Since the equipment would not have to be
mobile, its cost could be further reduced.
Fourth, seek an interested party to develop a mobile
processing plant. This option would
reduce handling and hauling costs and leave sand and aggregate product for
re-use by the Public Works Department.
A dry system would be the easiest and most versatile equipment to move
from facility to facility, but would require pre-drying of the vactor waste or
an alternate disposal option. Street
sweepings could be easily processed in the dry months without any
conditioning. A portable wet system
would be more cumbersome to move-in for small quantities. While it would produce a higher quality
product, the wash water treatment issues may make a portable wet system
impractical, especially in dealing with the small quantities in yearly
stockpile at most generator sites.
Last, the generator could screen the street waste
solids, and the screened material could be hauled to an asphalt plant
retro-fitted to burn hydrocarbons. All
the pre-screened street waste solids could be processed at an asphalt plant,
although at significantly higher cost.
4. Economic Evaluation
4.1 Basis
for Economic Evaluation
The previous section of this report discusses
alternative methods of separating street waste solids into usable components,
and provides recommendations for preferred processing systems. This economic evaluation considers the
following five processing systems:
1.
Existing
aggregate wash plant and concrete batch plant;
2.
Dedicated,
private receiving and processing site;
3.
Dedicated,
municipal receiving and processing site;
4.
Mobile,
private processing equipment; and
5.
Existing
asphalt plant to burn organics and hydrocarbons.
For each of these alternatives, the generator (i.e.,
municipality or private sweeper or vactor company) may also have the choice of
pre-screening the street waste solids at their own holding facility, and
transporting the finer material to the processing plant, and disposing of the
overs at their cost. Alternatively, the
generator could deliver the entire mix of materials, and let the processor
(either private or public) separate and dispose of the overs materials. The latter alternative will certainly cost
the generator more and would likely have additional regulatory compliance
issues and/or permit conditions.
The economics for each of the five recommended
processing alternatives also depend on the volume of material to be
processed. There is limited information
available on the actual amount of street waste solids generated state wide,
however two examples provide a basis for this economic analysis. First, the Snohomish County Road Maintenance
Division estimates that 4,500 tons of street sweeping material and 1,000 tons
of vactor waste were generated in 1996.
This amount of material is generated in unincorporated Snohomish
County. Second, the City of Bellingham,
Washington advertised for bids to receive and process street solids waste in
September 1996. The bid document
indicates that for all of Whatcom County, the estimated quantity of street
sweepings is 3,000 tons annually and vactor waste is 4,500 tons annually. The street sweepings will vary considerably seasonally, with much
of the material consisting of vegetative matter (leaves) during the fall
season. Therefore the actual tonnage of
street sweepings requiring reprocessing would be somewhat less.
The equipment and site requirements for this
evaluation were selected to accommodate this range of material processing
quantities.
4.2 Discussion
of Processing Costs
Each of the alternatives will necessitate a County
Health District materials recycling permit, either existing with revised
conditions or newly obtained. In the
event that a Conditional Use Permit is needed, the cost of obtaining such a
permit could easily range between $40,000 to $50,000, and could take between 12
and 24 months to complete, depending on zoning, jurisdiction and public support
or opposition.
In addition, each alternative will have different
investment requirements resulting from the purchase of land and new equipment
or the use of existing sites and equipment in other material processing
industries. Some of the alternatives
will also require the generator to pay a tip fee, while others assume the
generator will pay capital and operating expenses. For these reasons, a direct cost comparison is not possible
between the five alternatives. The
costs for each alternative are discussed in the following sections, and the
range of costs for each alternative are summarized in Section 4.3.
4.2.1 Existing Aggregate Wash Plant and Concrete
Batch Plant
Four approaches have been considered for using an
existing aggregate wash plant. These
are listed in Table 1, along with an estimated tip fee cost.
|
Table 1 - Existing Aggregate Wash Plant, Tip Fee Estimates |
|
|
Description |
Tip Fee (cost/ton) |
|
Materials
pre-screened by generator, blended with bank run material, and without
process water treatment. |
$5 – 10 |
|
Materials
pre-screened by generator, blended with bank run material, with process water
treatment. |
15 – 20 |
|
Materials
pre-screened by generator, not blended with bank run material, with process
water treatment. |
30 – 35 |
|
Materials
not pre-screened by generator, not blended with bank run material, with
process water treatment. |
40 - 45 |
4.2.2 Dedicated Private Receiving and Processing
Site
This second alternative assumes that an existing
site currently used for recycling various municipal solid waste materials
(e.g., construction, demolition and land clearing debris) could be used. The street waste solids would be separated
using either wet or dry technologies.
Table 2 estimates the tip fee for four alternative approaches.
|
Table 2 - Dedicated Private Receiving and Processing Site, Tip Fee
Estimates |
|
|
Description |
Tip Fee (cost/ton) |
|
Materials
pre-screened by generator, separated using an air classification equipment |
$25 – 30 |
|
Materials
pre-screened by generator, separated using a water based classification
system. |
30 – 35 |
|
Materials
not pre-screened by generator, separated using an air classification system. |
40 – 45 |
|
Materials
not pre-screened by generator, separated using a water based classification
system. |
50 - 60 |
4.2.3 Dedicated Generator Processing Site
Should a generator consider doing their own dry
processing, they will need a large enough facility to stockpile their yearly
supply of street waste solids to allow for drying during the dry season. With wet separation technologies, long term
storage would not be necessary, however some means of treating the process
water would likely be required. The
equipment needed for processing could be new or used.
Typical costs for equipment components for both wet and dry separation systems are provided Table 3 (based on prices quoted in heavy equipment catalogs). For the purposes of this analysis, it is assumed that the generator already owns a front-end loader.
|
Table 3 - Dedicated Generator Processing Site, New and Used Equipment
Prices |
||
Description
|
Used Equipment |
New Equipment |
|
Trommel
Screen equipped with feed hopper, flights and chains, and material out
conveyors. |
$40,000 |
$115,000 |
|
Small
air separator for processing post-screened street sweeping solids (dry) for
light air separation. |
20,000 |
35,000 |
|
Full
scale air separator de-stoner to process fine and coarse debris, for heavy
air separation. |
70,000 |
110,000 |
|
Fine
material sand screw for wet separation of 3/8-inch minus material, plus
discharge water clarifier |
10,000 |
30,000 |
|
Hydrobelt
type log washer, plus discharge water clarifier |
25,000 |
85,000 |
|
Flat
deck screen for separating coarse and fine aggregate |
15,000 |
50,000 |
|
Stacking
conveyors (2) |
5,000 |
15,000 |
The following costs for processing the materials
assumes that a total of 5,000 tons of street waste solids would be produced
annually, and that the equipment would have a life expectancy of 4 years for
used equipment and 8 years for new equipment.
The cost per ton to process the materials does not include the cost of
the processing site, as this would be variable between public and private generators.
In Table 4, heavy waste separation refers to
recovery of all aggregate materials, including cobbles and boulders which could
be crushed and used as aggregate.
Recovery of these heavy materials would offset the cost of disposal of
these materials. Conversely, light
waste separation refers to aggregate recovery from the 1-inch minus materials,
and substantially increased cost for overs disposal.
|
Table 4 - Dedicated Generator Processing Site, Operating Cost
Estimates |
||
Description
|
Used Eq. Operating Cost/ton |
New Eq. Operating Cost/ton |
|
Dry,
Heavy Waste Separation |
$17 |
$19 |
|
Dry,
Light Waste Separation |
18 |
20 |
|
Wet
Waste Separation, with Process Water Treatment |
22 |
25 |
These operating costs could be somewhat offset by
revenues or savings generated for the finished processed materials. In addition, the actual cost per ton would
increase with quantities less than the 5,000 tons assumed, and similarly would
decrease with quantities greater than those assumed.
4.2.4 Mobile Private Processing Equipment
The fourth alternative consists of the same basic
operations as described in the previous alternative, with the exception that
all of the equipment would be privately owned and mobile. In this case, the equipment would be more
costly to produce and the service offered would consist solely of separation of
materials, such that all separated materials and overs materials would be left
on site for the owner to utilize and dispose, respectively. The anticipated range of costs are presented
in Table 5.
|
Table 5 - Mobile Private Processing Cost Estimates |
||
Description
|
Low Cost/ton |
High Cost/ton |
|
Dry,
Heavy Waste Separation |
$30 |
$45 |
|
Dry,
Light Waste Separation |
25 |
35 |
|
Wet
Waste Separation, with Process Water Treatment |
35 |
50 |
4.2.5 Existing Asphalt Plant to Burn Organics and
Hydrocarbons
The cost of using an existing asphalt plant to burn
organics and hydrocarbons is currently $45 to $55 per ton of material
processed, for 1-inch minus soil. The
cost to process the unscreened material, and dispose of litter and other reject
materials would range between $60 and $75 per ton.
4.3 Conclusions
For the five alternatives
considered in this economic evaluation, the range of costs to process the
street waste solids materials are summarized in Table 6.
|
Table 6 - Summary Cost Estimates |
||
Alternative
Description
|
Low cost/ton |
High cost/ton |
|
Existing Aggregate Wash Plant and Concrete Batch
Plant |
5 |
45 |
|
Dedicated Private Receiving and Processing Site |
25 |
60 |
|
Dedicated Generator Processing Site |
17 |
25 |
|
Mobile Private Processing Equipment |
25 |
50 |
|
Existing Asphalt Plant to Burn Organics and
Hydrocarbons |
45 |
75 |
5. Full Scale Materials
Separation Test
5.1 Overview
To validate the premise that street waste solids can
be separated into constituent materials using a combination of separation
technologies, a full scale test was
conducted on Wednesday, May 14th, 1997, at Smokey Point Concrete, in Arlington,
Washington. The objectives of this test
were to:
·
remove
litter, oversized material, organics and silt from the sand and gravel
fractions;
·
estimate
relative quantities of reusable and discard materials;
·
evaluate
methods to improve the efficiency of the respective separation technologies;
·
determine
the level of contamination of the clean aggregate materials, in accordance with
the SHD Interim Policy.
Beginning in late April, 1997, the Snohomish County
Roads Maintenance Division coordinated the delivery of approximately 200 cubic
yards of street sweeping and vactor grit materials from a variety of
municipalities located throughout the western area of the County. These materials, when stockpiled, formed a
heterogeneous mix with varying quantities of litter, vegetative matter,
construction debris, large rock, and other discard materials. In most cases the material was wet, however
no free water was observed.
Prior to and during the test, photographs and video
footage were taken to document the event.
The test lasted approximately 4 hours, which provided sufficient time to
refine the method of operation and optimize the flow of materials through the
separation process.
5.2 Pre-Screening
The combined street waste solids were prescreened to
remove the 1-inch plus material. A
vibratory deck screen (Powerscreen) was used, and included a 4-inch grizzly for
separating the oversized contaminants and large rock, and a 1-inch deck screen
to separate the middle fraction. A Cat
988 Front End Loader was used to feed the material into the screen hopper.
At the outset of the pre-screening phase, a
Snohomish County 5-cubic yard dump truck was situated beneath the middle fraction,
side-discharge conveyor. During the
first hour of operation, it was observed that a moderate to high percentage of
reusable granular materials were being discharged along with the discard
material. When the first truck load of
discard materials were taken to the Arlington transfer station, approximately 4
cubic yards of the middle fraction was allowed to accumulate on the
ground. This material was then
re-screened, which reduced the discard pile size by approximately
one-third. The remainder of the
pre-screened material was processed twice to minimize the quantity of discard
materials.
The 1-inch minus material was discharged by the end
conveyor and allowed to accumulate in a large pile. This material was dark brownish-black in color, moist and well
graded. Organics consisted primarily of
dark fines, small sticks and pine needles.
Composite samples of this material were taken during the early, middle
and late stages of pile development, in accordance with the procedures
specified in the project sampling plan (as discussed in Section 5.4,
below). The prescreening operation
continued after the start of the wash and separation phase of the test.
5.3 Screen and Wash Separation Process
The 1-inch minus material was transported to the
feed hopper of the aggregate screen and wash plant using the Cat 988 Front End
Loader. The hopper metered the material
onto a conveyor which then delivered it to a wet screen located at the top of
the separation plant. The wet screen
accomplished a second stage separation into two size fractions, including a
coarse fraction consisting of 1-inch to ¼-inch, and a fine fraction consisting
of minus ¼-inch. The coarse fraction
was then directed to the log washer, and the fine fraction was directed to a
double sand screw separator.
The coarse fraction was introduced into the log
washer along a sloping, vibrating chute.
The method of separation in the log washer consisted of a set of sloping
conveyor-type screens rotating in the uphill direction and a set of 24 high pressure
nozzles pointed mostly in the downhill direction. The screens separated the coarser material into two components,
including the 1-inch to 5/8-inch fraction (“concrete rock”) and the 5/8-inch to
¼-inch fraction (“pea gravel”). The
water jets were very effective at removing the organics in the log washer, most
of which consisted of small sticks and bark. The organics remained in the wash
water that was returned to the settling pond.
The clean concrete rock and pea gravel were discharged onto separate
stacking conveyors.
The fine fraction from the second stage separation,
consisted of well graded sand and fine organics. This material was then further processed in a flow density
separator and a double sand screw separator.
The flow density separator generally operates with a sand and water
slurry flowing horizontally in a basin, with the flow passing over a vertical
baffle. With this arrangement, the
coarser sand falls out of suspension quickly and is trapped on the leading side
of the baffle and directed to a vertical discharge. Similarly, the finer sand carries over the baffle and is directed
to a separate discharge. The two
gradations of material are then directed into one side or the other of the
double screw separator. The flow of
liquid also serves to remove a large portion of the remaining fine organics,
and is returned to the wash water settling pond.
The double sand screw separator consists of a two
parallel, gently sloping, continuous helical screws, partially submerged in an
elongated tank or “washer box”. A feed
hopper is located at the low end of the device and receives a liquid slurry of
silty and fine granular material. A
water jet is located in the washer box to further remove residual fines. Each of the screws discharged onto stacking
conveyors.
5.4 Soil and Water Sampling
Samples of each of the unseparated and separated
soils were obtained during the test, in a manner that was consistent with
procedures used by Snohomish County Road Maintenance Division for their
analytical studies. The procedures for
preparing composite laboratory soil samples are summarized below.
1.
Obtain
three equal quantities of material from separate areas and depths of the pile
of material to be tested, and place in a mixing container or on a durable plastic
tarp.
2.
Stir
the mixture thoroughly, and remove sticks, organics, trash and rocks over
1/8-inch in diameter.
3.
Fill
laboratory prepared sample jars, tapping for compaction, and topping off to
minimize air space above the sample.
Seal the jars with an air tight lid, label completely and place in a
cooler with frozen cold blocks or ice.
Follow laboratory instructions for maximum holding times.
4.
Prepare
the Chain of Custody form immediately after each sampling.
Liquid samples were also taken; four on the day
preceding the test and three more on the day of the test. Three of the samples on the first day were
taken from points of discharge on the screen and wash separation
equipment. The three samples on the day
of the test were taken from the same locations. The fourth sample taken on the first day was obtained from the
wash water sediment pond.
All of these samples were obtained using the
following procedures:
1.
Fill
laboratory prepared sample jars directly at the point of discharge, topping off
to minimize air space above the sample.
2.
Seal
the jars with an air tight lid, label completely and place in a cooler with
frozen cold blocks or ice.
3.
Follow
laboratory instructions for maximum holding times.
4.
Prepare
the Chain of Custody form immediately after each sampling.
5.5 Observations and Conclusions
The breakdown of the constituents were visually
estimated as indicated in Table 7:
|
Table 7 - Estimated Proportion of Separated Materials |
||
|
Plus
1-inch |
10 percent of total pile. |
|
|
|
||
|
Of
the remaining 90 percent that passed the 1” screen: |
||
|
|
|
|
|
1
to 5/8-inch |
10 percent |
|
|
5/8
to ¼-inch |
15 percent |
|
|
Coarse
Sand |
35 percent |
|
|
Fine
Sand |
35 percent |
|
|
Organics
(sticks & leaves) and Silt |
5 percent |
|
The following observations were made during the
course of the full scale materials separation test:
·
The
full scale test was successful at demonstrating that organics and fines can be
effectively removed from the mineral sand and gravel fraction.
·
Pre-screening
of the street sweeping and vactor grit materials is essential to the overall
separation process. However, it would
likely be more efficient to use a self cleaning trommel screen instead of a
vibratory deck screen.
·
The
deck screen used during the test had a tendency to blind, resulting in
production delays.
Because of the heavy load of organics in the street
waste solids materials, it would be more effective to combine these materials
with other source materials prior to screening and washing. In this way, the percentage of organics
would be reduced in the process materials, and the efficiency of the total
system would be increased. While some
sticks made it through the process to both the concrete rock and pea gravel
piles, it is believed that virtually all of the sticks would be removed if the
organic loading was decreased.
Combining street waste solids with bank run material would require
special approval by the jurisdictional health districts and Ecology.
The wash water separates the organics and fines from
the sand and gravel fraction, and returns this material to the sediment
pond. Because of this and concerns over
TPH constituents accumulating in the pond, it would be appropriate to provide a
separate liquid post-processing system to remove the organics and TPH
products. This would also be a reason
to conduct additional field tests using dry separation technologies, including
vibratory and airflow separation in combination with mechanical screening. These tests were not conducted as part of
this project because of time and resource limitations.
6. Full Scale Test - Analytical Test Results
Samples of each of the pre-screened and clean,
separated soils were obtained during the full scale field test, as described in
Section 5.4 of this report. The
analytical test results for these samples are discussed below.
6.1 Soil Samples
Five soil samples were obtained at the time of the
full scale separation test, as described in Table 8.
|
Table 8 - Soil Sample Description |
|
|
Sample No. |
Sample
Description |
|
|
|
|
23S |
Minus
1-inch screened, not separated by wash plant |
|
24S |
Minus
1-inch to 5/8-inch, separated concrete rock |
|
25S |
Minus
5/8-inch to ¼-inch, separated pea gravel |
|
26S |
Separated
coarse sand |
|
27S |
Separated
fine sand |
The analytical test results for these samples are
presented on Table 2, and discussed below.
For all five samples, total metals, PAH’s and PCB’s
were either non-detectable or well below reportable levels.
As with the preliminary test results for the
laboratory separated sample, total petroleum hydrocarbons did exceed the
reportable level (200 ppm) in all five samples for heavy oil, using the WTPH
with acid cleanup method.. The
concentrations of heavy oil in the samples ranged from 230 ppm to 380 ppm,
which characterizes this material as a Class B soil, in accordance with the SHD
Policy, (i.e., Ecology - Class 3 soil).
Diesel was detected in both of the sand samples, at
concentrations below the reportable level (200 ppm). These concentrations were 41 ppm for the coarse sand and 74 ppm
for the fine sand.
6.2 Water Samples
Seven water samples were obtained of process water
at intake and discharge points in the processing equipment. These samples are described in Table 9
.
|
Table 9 - Water Sample Description |
|
|
Sample No. |
Sample
Description |
|
|
|
|
19L |
Log
Washer (1) |
|
20L |
Fines
material sand screw (1) |
|
21L |
Inlet
water (1). |
|
22L |
Sedimentation
/ Process Water Pond (1) |
|
28L |
Wet
sand density separator, that fed the fine material sand screw (2) |
|
29L |
Fine
material sand screw(2) |
|
30L |
Log
washer(2) |
|
|
|
|
(1)
Preceding the full scale field test |
|
|
(2)
During the full scale field test |
|
The analytical tests for these seven samples
consisted of TPH’s only, as these were the only constituents previously found
in any of the samples tested. For five
of the seven samples, both diesel and heavy oil were non-detected, and the
remaining two samples, diesel and heavy oil were very low, less than 3 percent
of the reportable levels.
6.3 Conclusions
The concentrations of heavy oil in the soil samples
ranged from 230 ppm to 380 ppm, which characterizes this material as a Class B
soil, in accordance with the SHD Policy.
Concentrations of diesel in all liquid samples were well below
reportable levels.
7. Summary of Conclusions
7.1 Previous Studies
Numerous studies have been completed by Ecology and
local municipalities to evaluate the character of street waste solids, and to
develop analytical methods for resolving the problems associated with false
positive laboratory test results.
Previous studies concluded:
·
Organic
(plant) material contributed to a false positive result with each of the three
total petroleum hydrocarbon (TPH) analysis methods used;
·
Sources
likely to contribute to TPH concentrations in street waste include organic
(plant) material, automobile and truck tires, asphalt paving materials, and
motor oil and lubricants from cars and trucks.
Relative amounts of contribution to the TPH concentration were not
identified.
·
Street
waste is a solid waste and is typically not a dangerous waste, and Ecology and
the SHD regulations support reuse of street waste.
·
Chemical
analysis results for metals do not exceed MTCA Method A soil cleanup levels or
SHD threshold criteria, and do not limit reuse options.
·
Chemical
test results for CPAH exceed SHD threshold criteria and may limit management
options to those associated with Class B material.
7.2 Street Waste Characterization
Preliminary tests conducted on one sample of street
sweeping material suggested that
organic materials could be separated from mineral constituents, and that the
mineral fraction was contaminated with total petroleum hydrocarbons, confined
to heavy oil, in concentrations below the reportable limits. Given these
preliminary test results, the separated mineral fraction could be used for any
of the Class A and Class B applications, as defined by the Snohomish Health
District Policy Statement regarding Street Waste Solids Recycling and
Disposal. In the event that future
samples showed heavy oil concentrations exceeding the 200 ppm criteria, then
these materials would be restricted to Class B reuse alternatives, which
consist primarily of encapsulation in concrete and asphalt products.
7.3 Separation Alternatives
Five alternative methods of material separation were
discussed, including the use of liquid, vibratory, and air separation,
mechanical screening, and combustion.
Considering the available technologies, five
alternative approaches for separating and utilizing the street waste solids are
recommended. The first recommendation
is to haul street wastes to existing aggregate wash plants equipped with wood
removal equipment, and blend these materials with daily process materials for
use as aggregate in concrete. To
accomplish this, it would be necessary to resolve regulatory issues with the
Jurisdictional Health Districts and Ecology regarding: 1) blending street waste
solids with bank run materials to facilitate separation; and 2) wash water
quality.
Second, seek an interested party to develop a
dedicated processing site for the street waste solids. The separation process may be a closed wash
system for all the street waste or a dry system with facilities to condition
the vactor waste before processing. A
centralized processing facility could be set up at one of the sites currently permitted
to take construction and land clearing debris.
To warrant the capitalization expense, multiple generators would have to
contract with a possible receiver as no single source has enough material to
create a large enough income stream.
Third, individual generators could purchase equipment
to process street waste for re-use at their facility. Because of the relatively small quantities produced by each
jurisdiction, small production rates would work and therefore small, less
expensive equipment would be required.
Since the equipment would not have to be mobile, its cost could be
further reduced.
Fourth, seek an interested party to develop a mobile
processing plant. This option would
reduce handling and hauling costs and leave sand and aggregate product for
re-use by the waste generator. A dry
system would be the easiest and most versatile equipment to move from facility
to facility, but would require pre-drying of the vactor waste or an alternate
disposal option. Street sweepings could
be easily processed in the dry months without any conditioning. A portable wet system would be more
cumbersome to move-in for small quantities.
While it would produce a higher quality product, the wash water
treatment issues may make a portable wet system impractical, especially in
dealing with the small quantities in yearly stockpiles at most generator sites.
Last, the generator could screen the street waste
solids, and the screened material could be hauled to an asphalt plant
retro-fitted to burn hydrocarbons. All
the pre-screened street waste solids could be processed at an asphalt plant,
although at significantly higher cost.
7.4 Economic Evaluation
For the five alternatives
considered in this economic evaluation, the range of costs to process the
street waste solids materials are summarized in the following table.
|
Table 10 - Summary Cost Estimates |
||
Alternative
Description
|
Low cost/ton |
High cost/ton |
|
Existing Aggregate Wash Plant and Concrete Batch
Plant |
$5 |
$45 |
|
Dedicated Private Receiving and Processing Site |
25 |
60 |
|
Dedicated Generator Processing Site |
17 |
25 |
|
Mobile Private Processing Equipment |
25 |
50 |
|
Existing Asphalt Plant to Burn Organics and
Hydrocarbons |
45 |
75 |
7.5 Full Scale Materials Separation Test
The full scale test was successful at demonstrating
that organics and fines can be effectively removed from the mineral sand and
gravel fraction.
The breakdown of the constituents were visually
estimated as follows:
Plus 1-inch 10
percent of total pile.
Of the remaining 90 percent that passed the 1”
screen:
1 to 5/8-inch 10
percent
5/8 to ¼-inch 15
percent
Coarse Sand 35
percent
Fine Sand 35
percent
Organics (sticks & leaves) and Silt 5 percent
Pre-screening of the street sweeping and vactor grit
materials is essential to the overall separation process. However, it would be more efficient to use a
self-cleaning trommel screen instead of a vibratory deck screen. The deck screen used during the test had a
tendency to blind, resulting in production delays.
Because of the heavy load of organics in the street
solids materials, it would be more effective to combine these materials with
other source materials prior to screening and washing. In this way, the percentage of organics
would be reduced in the process materials, and the efficiency of the total
system would be increased. While some
sticks made it through the process to both the concrete rock and pea gravel
piles, it is believed that virtually all of the sticks would be removed if the
organic loading was decreased.
Combining street waste solids with bank run material would require
special approval by the jurisdictional health districts and Ecology.
The wash water separates the organics and fines from
the sand and gravel fraction, and returns this material to the sediment
pond. Because of this and concerns over
TPH/PAH constituents accumulating in the pond, it would be appropriate to
provide a separate liquid post-processing system to remove the organics and
contaminant products. This would also
be a reason to conduct additional field tests using dry separation
technologies, including vibratory and airflow separation in combination with
mechanical screening.
7.6 Full Scale Test - Analytical Test Results
The concentrations of heavy oil in the soil samples
ranged from 230 ppm to 380 ppm, which characterizes this material as a Class B
soil, in accordance with the SHD Policy.
Concentrations of diesel in all liquid samples were well below
reportable levels.
8. Acknowledgments
This Report was funded by the Recycling Technology Assistance Partnership (ReTAP). ReTAP is a program of the Clean
Washington Center, Washington State’s lead agency for the market development of
recycled materials. ReTAP is an
affiliate of the national Manufacturing Extension Partnership (MEP), a program
of the U.S. Commerce Department’s National Institute of Standards and
Technology. The MEP is a growing
nationwide network of extension services to help smaller U.S. manufacturers
improve their performance and become more competitive. ReTAP is also sponsored by the U.S. Environmental
Protection Agency and the American Plastics Council.
The following organizations contributed their time,
effort, and support during the conduct of this project:
Snohomish County Roads Maintenance Department,
Snohomish, Washington
Land Technologies, Inc. of Arlington, Washington
Price-Moon Enterprises of Snohomish, Washington
In addition, special thanks are extended to the
following companies for the time and resources that they so graciously donated
to this project:
Smokey Point Concrete, Arlington, Washington for
providing equipment and manpower to conduct the full scale separation test.
McClanahan Corporation for providing information on
fine material screws, log washers and for conducting preliminary laboratory
separation tests of street sweeping and vactor grit materials.
General Kinematics Corporation for providing
information and a prototype design for a “Vibratory Air Knife Separator”.
Cities of Arlington, Everett, and Mount Lake
Terrace, Washington for providing street sweepings for the full scale
separation test.
Appendix A
Snohomish Health District Policy Statement
Regarding Street Waste Solids Recycling and Disposal
SNOHOHOM!SH
HEALTH
DISTRICT
SNOHOMISH HEALTH DISTRICT 95-11
RESOLUTION OF THE BOARD OF HEALTH
RESOLUTION
NUMBER: 95-11
RESOLUTION SUBJECT: STREET WASTE SOLIDS RECYCLING
AND DISPOSAL GUIDANCE
WHEREAS the Board of Health of the Snohomish Health District serves to promote the public health of the residents of Snohomish County, and
WHEREAS the Board of Health recognizes the need, as outlined in the Snohomish County Moderate Risk Waste Management Plan, for local best management practices concerning recycling and disposal alternatives for street sweepings, vactor grit solids and ditch cleanings (collectively referred to as "street waste solids"), and
WHEREAS the Snohomish Health District has written and adopted a widely accepted countywide policy addressing this issue, but recognizes that uniform statewide implementation of best management practices concerning recycling and disposal alternatives for street waste solids is needed, and
WHEREAS the Washington Department of Ecology is the most appropriate agency to develop an effective statewide policy, and
WHEREAS such a policy should take into consideration the need for refined laboratory test methods for these wastes which can accurately quantify petroleum contamination levels without interference from naturally occurring vegetative debris, and
WHEREAS the Washington Department of Ecology has also recognized the need for revised test methods and a statewide street waste solids recycling and disposal policy,
NOW THEREFORE the Board of Health hereby adopts this resolution encouraging the Washington Department of Ecology to continue to give priority to the research of laboratory test methods that could be used to accurately detect petroleum contamination in street waste solids, and the associated development of statewide best management practices concerning recycling and disposal alternatives for street waste solids.
ADOPTED this 11th day of April.
1995.
SNOHOMISH POLICY
STATEMENT REGARDING
HEALTH Street
Waste Solids
DISTRICT Recyci
mg and Disposal
3020 Rucker Environmental Health Division
Everett, WA 98201 Solid
Waste and Toxics Section
(206)
339-5250
BACKGROUND
Solids collected during the
cleaning of storm sewers, streets and drainage ditches (collectively referred
to as "street waste solids") have often been used in the past by
generators as general purpose fill material. However, street waste solids fall
within the state definition of solid waste established under RCW 70.95.030, and
typically fail Model Toxics Control Act standards for total petroleum
hydrocarbon (WTPH 418.1 Modified) levels. As such, many generators are now
disposing of this material in landfills at considerable (and many believe
unjustifiable) expense.
The State's Solid Waste
Management Act, Chapter 70.95 RCW, promotes waste recycling (rather than
landfill disposal) among its highest waste management priorities. The Snohomish
Health District (Health District), in accordance with the Department of
Ecology's (Ecology) waste reduction and recycling objectives, is therefore
promoting recycling options for street waste solids which protect both public
health and the environment.
POLICY STATEMENT
It is not the intent of this
policy to establish a Health District program for formally regulating this type
of material through a permit or routine inspection program. However, this interim policy will serve to
guide Health District staff in assessing and directing street waste solids
disposal and/or recycling situations, on a complaint basis or when a request
for assistance is received from a generator. This policy will remain in effect
until a statewide guidance policy is promulgated by the Department of Ecology
or until the policy is rescinded by the Health District.
It should be noted that this
policy has not been formally adopted or endorsed by the Department of Ecology.
However, this interim policy was developed in cooperation with Ecology
personnel responsible for solid waste policy development, and the contamination
levels and end-uses for street waste solids outlined in this document were
originally drafted by Ecology staff.
The Health District believes the criteria contained in this interim
policy meet with the Department of Ecology's approval.
It should also be noted that
the Health District recognizes concerns expressed by many street waste solids
generators regarding possible interferences (i.e. "false positives"
resulting from the presence of vegetative matter) when using test method WTPH
418.1 Modified. The Health District supports the generators efforts, through
the work of the Snohomish County Vactor Grit Task Force, to resolve this issue
to the satisfaction of both the generators and the Department of Ecology. Resolution of this question, and reliance
upon a different test method for characterizing street waste solids, may allow
additional recycling opportunities for this material that are not currently
outlined in this policy.
WASTE CHARACTERIZATION
Test data indicate that most
street waste solids are typically not dangerous (hazardous) waste as defined by
the State Dangerous Waste Regulations, Chapter 173-303 WAC. Therefore, routine
testing of street waste solids for dangerous waste criteria is not typically
necessary. However, if the waste collector finds upon visual inspection that
the waste exhibits unusual characteristics that would indicate excessive
pollution, that waste should be handled by following accepted spill response
protocol, or appropriate precautions should be taken to segregate the
contaminated materials until they can be properly characterized and disposed of
as a dangerous waste. Indications that a street waste solid may be a dangerous
waste include an obvious odor of gasoline or other volatile solvents; obvious
pooling or accumulation of petroleum products upon visual inspection; suspicion
of the presence of extremely acidic or alkaline materials; signs of chemical
reaction, etc.
Testing of street waste
solids for other constituents not necessarily specified in the State Dangerous
Waste Regulations is necessary in
order to determine contamination levels and identify appropriate end-uses as
outlined in this policy. Sampling plans
can be developed following guidelines for collecting samples from piles of
contaminated soils, as outlined in the Department of Ecology's, Guidance for
Remediation of Petroleum Contaminated Soils. 91-30, or sampling plans can
be individually developed with assistance from the Health District. Unless
there is reason to suspect that other contaminants may be present, samples
should be analyzed for TPH (using WTPH 418.1 Modified), plus the following
metals: arsenic, cadmium, chromium, lead, and inorganic mercury (using
"total metals" analysis). If
test results -consistently show the same outcome, the Health District will
consider a reduction in the frequency, constituents or number of samples
analyzed, as proposed by the generator.
STORAGE
Piles of contaminated street
waste solids must be placed on a liner, such as asphalt, concrete, or other
impervious material, to collect and control any liquids associated with the
pile. Surface water run-on and run-off from the piles must be controlled and
managed as required by State Water Quality Regulations to prevent surface and
groundwater quality degradation. Generally this will be accomplished by
covering the piles with plastic tarps during rainy periods, to prevent water
infiltration and the possible production of contaminated run-off from the
piles. Piles established on an impervious surface which drains to a sanitary
sewer (i.e. sewage treatment plant) need not be covered. Appropriate steps must
also be taken to contain and dispose of liffer or other garbage associated with
the street waste solids.
It is recommended that
street sweepings and vactor solids be stored in separate piles, due to the
potential for differing levels of contamination. If vactor solids are being stored in conjunction with an
operating vactor decant station, the dewatered solids should be stored as
described above to prevent surface or groundwater quality degradation.
EXCLUSION
Street waste solids may be excluded from regulation
as solid waste by the Snohomish Health
District if it can be shown that:
1 ) The
collected or processed solids consist only of soils, sands, gravels or
sediments, and garbage, refuse, vegetative debris and other solids contaminants
have been removed; and
2 ) Free liquids have been removed and
appropriately treated and/or disposed of and
3 ) Concentrations of chemical contaminants do not
exceed cleanup values identified in Table 2, Method A Cleanup Levels - Soil, of
the Model Toxics Control Act Cleanup Regulation (MTCA), WAC 173-340-740. (See Table 2 of this policy for partial list
of contaminants.)
Street waste solids must be
handled as solid waste until it is determined that this exclusion applies. Such solids that have been excluded from
solid waste regulation by the Snohomish Health District may be used in any
manner that would not cause a threat to human health or the environment. In keeping with established Ecology
guidelines, the Health District recommends that these solids not be used in or
adjacent to wetlands, surface water, groundwater, drinking water wells, or
plastic pipes carrying drinking water.
The Health District also recommends that they not be used near food crop
growing areas, as residential topsoil or for other residential uses.
In addition, the Health
District recognizes that street sweepings collected at certain times of the
year may be nearly or entirely vegetative matter (e.g. fallen leaves, needles
and branches), as opposed to potentially contaminated soil, rock and grit.
Likewise, some jurisdictions may have the equipment to separate out vegetative
matter from mineral constituents. In instances when segregated or collected
street waste solids contain little soil (i.e. less than 10% by volume), these
wastes may be managed as yard debris and would not be subject to the sampling
and testing requirements of this interim policy The material managed as yard debris must be taken to a permitted
or approved composting facility, composted by the municipality according to a
plan of operation acceptable to the Health District, or otherwise properly
managed as yard waste.
Furthermore, it is the
Health District's understanding that roadside ditch cleanings are unlikely to
be contaminated unless such material is associated with a stormwater
retention/detention system, a "biofilter" system or has been
contaminated by a spill or other release.
As such, ditching material not associated with one of these systems and
presumed to be uncontaminated is excluded from this policy. Typically, clean
ditching material can be segregated into vegetative and soil fractions, and
recycled as yard waste (the sod fraction) and "clean" soil. Ditching material that may be contaminated
must be stored, tested and handled in the same manner as other street waste
solids covered under this policy. It is
the generator's responsibility to visually inspect and otherwise determine
whether the ditching material may be contaminated.
RECYCLING
The State's solid waste
statute, Chapter 7O~95 RCW, prioritizes the need to recycle rather than dispose of waste. When considering recycling options for street waste
solids, contaminant levels must be considered to insure that the final end-use
does not compromise the health of the public or the environment. Until such waste is recycled, it continues
to be regulated as solid waste. The following
are options for street waste solids recycling:
CLASS "A" STREET
WASTE SOLIDS
Class "A" street
waste solids are those solids whose contaminants do not exceed levels
established in Table 1 of this interim policy, and (for contaminants not identified
in Table 1) whose levels do not exceed cleanup levels identified in Table 2,
Method A Cleanup Levels - Soil, of the Model Toxics Control Act Cleanup
Regulation, WAC 173-340-740. Street waste solids must be tested to determine a
baseline for levels of regulated contaminants. (Refer to the Waste
Characterization section of this policy for information concerning testing.)
POTENTIAL END USES - CLASS "A" STREET
WASTE SOLIDS:
· Road
subgrade, parking lot subgrade, or other road construction fill. Must be used
under or incorporated into asphalt or concrete paving, and the road must have a
design which meets standards and specifications of the local jurisdictional
authority (1)
· Reuse
as street traction sand (1)
· Pipe
bedding - excluding bedding around plastic (e.g. PVC, polyethytene) pipe used
to convey drinking water (1) (2).
· Utility
trench backfill - excluding backfill around plastic (e.g. PVC, polyethylene)
pipe used to convey drinking water (1) (2).
· Controlled
density fill - utilizing a design which meets standards and specifications of
the local jurisdictional authority (1) (2).
Fill in commercial or
industrial zones (1) (2) (3).
· Any
option approved for recycling of Class "B" street waste solids.
· Other
end-use as approved by the Snohomish Health District.
Class "A" street
waste solids cannot be reused for the end-uses listed above if they would be
placed in an area which is likely to result in the contamination of ground or
surface water, or lead to other potential environmental or public health
problems (for example, a roadside ditch likely to convey water).
1) Would first require removal of litter and
vegetative matter.
2) The end-use should take into consideration
potential human contact exposure both at the time of use and in the future.
3) This end-use requires the
following actions be taken:
(a) Completed fill must be
"encapsulated" with two (2) feet or more of uncontaminated, relatively impervious soil.
(b) Completed fill site must be recorded on Deed with Snohomish County Auditor's Office, to
include the following
information:
· Tax l.D. Number(s) for fill
area.
· General description of fill location
on tax lot, attach map.
· Certification Statement
regarding contaminant levels, for example:
"I certify that
the Class A street waste solids disposed here meet contaminant levels specified by Snohomish
Health District's Interim Policy Concerning Street Waste Solids Recycling and
Disposal. This determination has been made under my direction and supervision
in accordance with the system designed to ensure that qualified personnel
properly gather and evaluate the information used to determine that the Class A
Street Waste Solids contaminant levels have been met."
NOTE: All recycling end-uses
must be conducted in compliance with
specifications required by federal, state or local regulations, or
specifications required by
a facility, manufacturer or vendor accepting the
street waste solids for processing or recycling.
Although use of Class
"A" street waste solids in the manners outlined above is accepted as
a prudent end-use by the Health District, certain end-uses may not be
consistent with the Model Toxics Control Act Cleanup Regulation. Generators interested in pursuing these options
are therefore advised to seek independent legal counsel before proceeding.
CLASS "B" STREET
WASTE SOLIDS
Class "B" street
waste solids are solids whose contaminant levels exceed Class "A"
street waste solids contaminant levels, but do not designate as dangerous waste
under Chapter 173-303
WAC.
POTENTIAL END-USES - CLASS
"B" STREET WASTE SOLIDS:
· Pre-fab concrete
manufacturing. NOTE: Facility
manufacturing concrete must, in most instances, submit recycling permit application to
the Health District for review and approval.
· Portland cement manufacturing. NOTE:
Facility manufacturing cement must, in most instances, submit recycling
permit application to the Health District for review and approval.
· Asphalt manufacturing.
NOTE: Facility manufacturing
asphalt must, in most instances, submit recycling permit application to the Health
District for review and approval.
· Treatment at a contaminated soil treatment facility. NOTE:
Facility treating contaminated soil must, in most instances, submit an application to the
Health District for review and approval.
· Daily cover or fill in permitted municipal solid
waste landfills, provided that the street waste solids have been dewatered.
Class "B" street waste solids cannot be used for final cover during a
landfill closure.
· Other end-use as approved by the Snohomish
Health District.
INAPPROPRIATE END-USES - CLASS "A" and CLASS "B" SOLIDS:
· Department of Natural Resources surface
mining reclamation (for example, gravel pit
reclamations not specifically permitted as solid waste
disposal sites).
· On-site sewage disposal sand filter and/or
mound system construction.
· Cover or fill
in an inert-demolition waste landfill.
DISPOSAL
Untreated street waste
solids destined for final disposal may only be disposed in a permitted
municipal solid waste landfill, provided that they have passed the visual
insp~ction for dangerous waste identification, and have been dewatered.
Robert
A. Pekich, Director
Environmental Health
Division
Effective Date: January 1, 1995
TABLE 1
MAXIMUM END-USE CONTAMINANT LEVELS FOR
VACTOR AND STREET SWEEPING SOLIDS
ANALYTE ANALYTICAL METHOD MAXIMUM LEVEL
(ppm)
HeavyFuel WTPH 418.1* 2000
Hydrocarbons Modified
(C24-C30)
Diesel WTPH-D 500
(Cl 2-C24)
Gasoline WTPH-G 250
(C6-C1 2)
Benzene 8020 0.5
Ethylbenzene 8020 20
Toluene 8020 40
Xylenes (total) 8020 20
Contaminants not identified
in Table 1 must meet levels established in MTCA Method A Cleanup Levels - Soil
(Refer to Table 2 of this document).
To support the
accuracy of test results, alternative testing protocols may be substituted upon
approval by the Snohomish Health District.
* The Health District recognizes
concerns expressed by many street waste solids generators regarding possible
interferences (i.e. "false positives" resulting from the presence of
vegetative matter) when using test method WTPH 418.1 Modified.
TABLE 2
MODEL TOXICS CONTROL ACT (CHAPTER 173-340 WAC)
METHOD A CLEANUP LEVELS - SOIL
ANALYTE ANALYTICAL METHOD MAXIMUM LEVEL
(ppm)
Arsenic Total Metals
Analysis 20
Cadmium Total Metals
Analysis 2.0
Chromium Total Metals
Analysis 100
Lead Total Metals Analysis 250
Mercury Total Metals
Analysis 1.0
(Inorganic)
PAHs 8270 1.0
(Carcinogenic)
PCB Mixtures 8080 1.0
TPH
(Heavy WTPH
418.1 200
Fuel
Hydrocarbons) Modified
TPH
(Diesel) WTPH-D 200
TPH (Gasoline) WTPH-G
100
NOTE: Refer to Table 2, Method A Cleanup Levels - Soil, of the Model Toxics Control Act Cleanup Regulation, Chapter 173-340-740, for complete listing of substances.
121
394/dmb
Appendix B
Summary and Conclusions (Section 5) and the
List of References (Section 6) from
Snohomish County Street Waste Characterization
5.0 SUMMARY AND CONCLUSIONS
Samples of street waste (street sweeping and vactor solids) were obtained from three routes, two from the City of Everett and one from County Roads, during winter, summer, and autumn 1995. Samples were collected from material staged at City of Everett and Snohomish County both before and after processing of street waste to remove debris. The samples were tested for metals, 'PH, and PAL' to evaluate potential contaminants. The effect of composting or decomposition was evaluated by using concentrations before and after processing. Samples of reference materials such as asphalt, automobile tires, and organic material were analyzed and compared to actual street waste samples. Regulations from solid waste, toxics cleanup, and water quality areas were reviewed for potential application to street waste.
Conclusions are organized to address the objectives identified in Section 1.0. Conclusions associated with the chemical characterization information objective include:
· Metals, TPH, and CPAH were detected in street waste samples.
· No seasonal differences were identified.
· No consistent route differences were identified.
· Organic (plant) material contributed to a false positive result with each of the three TPH analysis methods used.
· Method WTPH-D (extended) with a sulfuric acid cleanup step typically provided the lowest TPH result and was the best of the three evaluated methods for minimizing the false positive contribution to the TPH result.
· Method WTPHAI8.1 typically provided the highest TPH result of the three methods.
· WTPH-D (extended) chromatograms show a single broad peak that was interpreted to be associated with a refined or processed hydrocarbon material. The similarity of the street waste peak with the used automobile tire reference material peak suggested a significant contribution from tires to street waste.
· WTPH-D (extended) chromatograms show that the reported diesel range TPH results were not diesel fuel.
· Sources likely to contribute to TPH concentrations in street waste include organic (plant) material, automobile and truck fires, asphalt paving materials, and motor oil and lubricants from cars and trucks. Relative amounts of contribution to the TPH concentration were not identified.
· Sources likely to contribute PAH and CPAH to street waste include automobile and truck tires, heavy oils, and asphalt paving materials.
Conclusions associated with the regulatory framework applicable to test results include:
· Street waste is a solid waste and is typically not a dangerous waste, and Ecology and SHD regulations support reuse of street waste.
· Chemical analysis results for metals do not exceed MTCA Method A soil cleanup levels, SLID threshold criteria, and do not limit reuse options.
· Chemical test results for CPAH exceed SHD threshold criteria and may limit management options to those associated with Class B material such as disposal at a solid waste landfill.
· Chemical analysis results for TPH in all samples (including organic material) using each of the three methods exceed MTCA Method A cleanup levels for TPH (diesel and other) referenced by SHD (1995).
· WTPH-D (extended) oil range hydrocarbon results (95 percent UCL on mean) are less than the SLID (1995) heavy hydrocarbon level.
· Without the acid cleanup TPH analysis method, TPH results would exceed the SLID threshold criteria and may limit management options to those associated with a Class B material.
· MTCA regulations do not apply directly to management of street waste. Risk-based exposure estimates (using an approach such as that in the MTCA regulations) allow possible future cleanup liability to be considered if material were placed in selected hypothetical exposure settings.
· Risk-based exposure estimates and comparison with MTCA residential and industrial soil cleanup levels show that CPAH concentrations in street waste material may not be acceptable for residential settings but may be acceptable for reuse in settings such as recreational, commercial, and industrial.
Conclusions associated with the management (and reuse) alternative information objective include:
· Composting contributes to a decrease in detected TPH concentration. Greater TPH concentration reductions are anticipated if more time for composting is
allowed before samples are collected and if larger organic material is retained and not removed by screening until composting has been completed.
· Risk-based analysis may be useful in evaluating possible settings for reuse of street waste material (as alternatives to more expensive landfill disposal).
In addition to these conclusions, several issues were identified which were beyond the scope of the present project. These issues include the effect of composting duration on 'PH and CPAH concentrations, urban soil background levels, and regulation of diesel range hydrocarbons that are not diesel fuel.
We trust that this information meets your needs. We appreciate the opportunity to provide environmental consultation to Snohomish County Solid Waste Management Division. Please contact us if you have questions.
LANDAU ASSOCIATES, NC.
By:
Brian F. Butler, Project Manager
and
Nancy B. Ball, Ph.D.
Senior Chemist
6.0 REFERENCES
Carrell, R. 3 May
and 25 July 1995. Personal communication (conversation with B. Butler, Landau
Associates, Edmonds, WA regarding WTPH analytical method change). Washington
State Department of Ecology.
Ecology. 1995. Best Management Practices (BMPs) for
Management and Disposal of Street Wastes. Draft. Washington State
Department of Ecology1 Water Quality Program. July.
Ecology. 1994. Guidance
for Remediation of Petroleum Contaminated Soils. Washington State Department of
Ecology.
Ecology. 1993a.
MTCA-STAT. July.
Ecology.
1993b. The Model Toxics Control Act Cleanup Relations. Chapter 173-340
WAC.
Washington State
Department of Ecology, Toxics Cleanup Program. Publication No. 9&06.
Amended December.
Ecology. 199la. Total Petroleum Hydrocarbons Analytical
Methods for Soil and Water. Guidance for
Remediation of
Releases from Underground Storage Tanks. Appendix L. Washington State
Department of
Ecology. April.
Ecology. 1992b. Statistical Guidance for Ecology Site
Managers. Washington State Department of Ecology, Toxics Cleanup Program.
August.
EPA. 1991. Human Health Evaluation Manual, Supplemental
Guidance: "Standard Default Exposure Factors." Office of Solid
Waste and Emergency Response, U.S. Environmental Protection Agency, Washington,
D.C. OSWER Directive 9285.64)3. March.
EPA. 1990. National Oil and Hazardous Substances
Pollution Contingency Plan. Final Plan. U.S. Environmental Protection
Agency. Federal Register 55(46): 8665-8865.
EPA. 1989. Risk Assessment Guidance for Superfund. Volume
1: Human Health Evaluation Manual
(Part A). Interim
Final. Office of Emergency and Remedial Response, U.S. Environmental
Protection Agency,
Washington, D.C. EPA/540/1-89/002. July
EPA. 1986. Test Methods for Evaluating Solid Waste. SW-846,
third edition with updates. U.S. Environmental Protection Agency.
Calvin, David V.
and Richard K Moore. 1982. Toxicants in
Urban Runoff - Metro Toxicant
Program Report #2, Toxicant Control Planning Section, U.S. Environmental Protection
Agency.
December.
Hepp, M. 8
December 1995. Personal communication (conversation with B. Butler, Landau
Associates, Edmonds, WA).
IRIS. 1995.
Integrated Risk Information System, National Library of Medicine. Bethesda, MD.
December Landau Associates, Inc. 1995a. Letter from B. Butler to M. Perla
(Snohomish County) regarding project scope. February 1.
Landau Associates,
Inc. 1995b. Street Waste Characterization
Project, Report of Winter 1995 Chemical Analysis Results. Landau
Associates, Inc. Edmonds, Washington. May 12.
Landau Associates,
Inc. 1995c. Street Waste Characterization
Project, Report of Summer 1995 Chemical Analysis Results. Landau
Associates, Inc. Edmonds, Washington. October 27.
Landau Associates,
Inc. 1995d. Street Waste Characterization
Project, Transmittal of Autumn 199 Chemical Laboratory Data Sheets. Landau
Associates, Inc. Edmonds, Washington. December 11
San Juan, C. 1994.
Natural Background Soil Metals Concentrations
in Washington State. Washington State Department of Ecology 9&115.
Shaheen, D. 1975. Contributions of Urban Roadway Usage to
Water Pollution. Washington, D.C.
U.S. Environmental
Protection Agency, Office of Research and Development (EPA-60O/2-754)04~
346 pp.
SHD. 1995. Policy Statement Regarding Street Waste
Solids, Recycling and Disposal. Snohomish
Health District,
Environmental Health Division, Solid Waste and Toxics Section, Everett, WA
January 1.
SWMD. 1995a.
Memorandum from M. Perla to S. Johnson (Snohomish County Council regarding VGTF
study update July 31.
SWMD. 199Sb.
Letter from M. Perla (Snohomish County Solid Waste Management Division to B.
Butler ~andau Associates) regarding additional chemical analyses. August.
W & H Pacific.
1994. Final Report: Vactor and Street
Sweeping Treatment, Recycling and Disposa Options, Snohomish County, WA. February
16.
Zemo, D.A., J.E.
Bruya, and T.E. Graf. 1995. The Application of Petroleum Hydrocarbor
Fingerprint
Characterization in Site Investigation and Remediation. Ground Water Monitoring
Review. pp.147-156.
Spring.
Appendix C
Snohomish County Public Works, Road Maintenance Division
Laboratory Test Results and Sweeping Testing
Interim Report



Snohomish County
Public Works
Road Maintenance Division
Sweepings Testing Interim Report June
26, 1996
Background
Pursuant to the issuance of Snohomish County Health
District (SHD) Policy on Street Waste Solids Recycling and Disposal, in
January, 1995, we have constructed containment facilities, treated and tested
2,600 CY of street sweepings. In the spring of 1995, existing sheds at three
locations were modified to accommodate storage of this material on asphalt
pads, under roofs and with controlled drainage. The volume soon exceeded this
capacity, due to lack of viable reuse options, and the sweepings were
stockpiled in open yard space. This report will address three phases of the
program which has been pursued to determine how this material can be reused.
Initial Characterization
The 1,600 CY of sweepings accumulated from January to
June, 1995, were screened and stored in inside and outside stockpiles. In
August, 1995, base line samples were
taken for laboratory analysis from pre and post screened material. Six samples
were taken for sieve analysis and % organic content as shown on Sheet 2.
Results of this initial testing eliminated the potential for reusing the
screenings incorporated with feed stock for asphalt production; due to
excessive organic content, which ranged from 4.2% to 13.4%. Laboratory testing
using the criteria in Table 2, MTCA Method A Soils Cleanup, SHD Policy, showed
NO contamination other than Heavy Oil (C24-C34) hydrocarbons, after using the
acid cleanup step with the WTPH-D Extended method.
Efforts were initiated to find a way to physically
separate the screened material by particle size and separate fractions. After
researching national sources and talking to five vendors/consultants with
environmental expertise, it was apparent that no current technology was
available to perform the separation. In October, 1995, samples were taken for experimental bench testing of the
physical separation concept, with encouraging results; both physically and
chemically. In January, 1996, a Clean Washington Center Technology Validation
Project Grant proposal was submitted for a development project.
The outside pile of 835 CY was screened in 33.2
machine hours, 58 man-hours, at a rate of 23 CY/IHr. That effort produced 80 CY
of trash or 10% trash. The screenings are fairly uniform
in composition and particle size, however still
contain excessive organics, plainly visible, as well as trash particles and
chips of the yellow chromate rpm's.
The inside pile of 765 CY was screened in 25.2 machine
hours, 44 man-hours, at a rate of 33 CY/IHr. That effort produced 30 CY of
trash or 4% trash. Screening the dry materials went through the screen quicker
than the wet; however, it seems that protection from the weather aided the
decomposition of the inside pile, since the composition of the original
materials had to be fairly uniform.
Followup Testing
Twenty three samples have been taken for
laboratory analysis; before and after screening some of the material, from
material which has been stockpiled uncovered and covered, over months of time
and that which was recently screened. Sheets 1, 3, 4 & 7 show the test
results. The quantifying analysis, which I did on the initial completion of
screening the sweepings from early in 1995, showed that the decomposition of
covered piles is accelerated over the uncovered piles. The stockpile which had
been under roof produced 4% trash off the screen, by volume. The uncovered
stockpile produced 10% trash by volume. Seven samples taken from the covered
piles, over eight months, average 46 ppm diesel and 357 ppm heavy oil after the
WTPH-D ext Cleanup testing. These appear to be residual contamination since the
diesel deviation is only ±7 ppm and the heavy oil is + 143 and - 167 ppm. Although there is no laboratory
test available to prove it; I am fully convinced that any lingering heavy oil
result is mostly asphalt particles. Charts #2 & 3 show the graphic
results of the diesel and heavy oils values. The graphics demonstrate the
difference between the D-ext test and the Cleanup for both products; however
there are still false positives in the latter, proven by lab testing of 100%
organic samples.
The remaining analytes
identified in Table 2 of the reference follow:
WTPH-G was not run on these samples as
no volitles were suspected.
PAH test results were well below the
reportable 1.0 ppm range. The maximum value of the eighteen compounds in the test parameters of
0.37 was defined from sample #16 as pyrene.
The majority of the mini
spikes, shown on chart #1, are pyrene. Over half of the samples show less than
0.15 ppm.
PCB testing was included in twenty one
samples and no detects were identiied for any of the seven compounds per sample.
Metals testing for the five elements
had some random values detected, however none of the results exceeded the
reportable limits for the respective elements, shown on chart #4.
The
results of the above testing should demonstrate that a baseline program has
been established in Snohomish County for street sweepings, which defines that
this material, when screened, can be used for general purpose fill in
industrial and commercial sites as described in the reference.
Composting
We have a test pile of mixed material; 25% each of screened sweepings,
screenings from log yard, sawdust and chicken manure, which has been composting
since early November, 1995. The test is ongoing at this time. Six samples have
been taken, two each at 60 day intervals. Samples # 12, 13, 18, 19, 28 & 29
on the tables and graphics are from this high organic mixture. At this time, after
six months decomposition and pile rotation eight times, the current testing
methods and standards will not allow rich organic compost to achieve the 65 PPM "Clean" threshold.
Summary
Working closely with the SEID, we have been successful
in reusing sweepings for two specific projects; building a berm and top
dressing on reclamation slopes, both of which were encapsulated by
hydroseeding.
We have been successful in achieving the CWC grant
assistance to conduct the Street Wastes Reprocessing and Reuse Project (SWRRP)
which will include vactor grit and sweepings. The one year contracted
performance period started on June 24, 1995.
win6/datalswwaste~swtstrpUbc/hd
Appendix D
Eco-Block Manufacturing as an Alternative Catch Basin
Waste Disposal Method
Eco-Block Manufacturing
as an alternative
Catch Basin Waste Disposal
Method
November 13, 1996
In late 1994 we
began to investigate methods of disposal for waste material removed from
stormwater catch basins and control structures throughout Kitsap County. Study
revealed the cost of disposal at the local landfill to be $39.95 per ton. At
this tonnage rate, the tipping fees for the contaminated material would be
approximately $6,800.00 per 100 cubic yards. $9,000.00 includes truck time and
driver wages for a total of$15,800.00. It was decided at that time that further
analysis was in order to find a less expensive means of disposal.
Since the fall of 1994, an experimental method of
disposal has been introduced with notable success, both logistically and
financially. The material removed from catch basins and control structures is
being cast into concrete Ecology Blocks. A surplus concrete mixing machine
purchased from the U.S. military was brought to the Central Kitsap Treatment
Plant. Repairs and refinements were made to the machine, for total outlay of
$1,000.00. Concrete forms were constructed with steel and materials purchased
at auction for $1,000 and production was begun.
In the first eleven months
of 1996 seventy-nine stormwater control structures and 1254 catch basins were
cleaned. This maintenance operation generated 417 tons of waste material. Two
hundred sixty blocks were produced, using 390 tons of the waste. Each block
uses 3,000 lbs. of the catch basin waste and 5 sacks of cement at $5.00 per sack. Total expenditure for
cement at that point was $6,500.00. After
a few initial castings, it was found necessary to add some washed rock to the
casting mix to achieve a suitable strength. Approximately 1/10 cubic yard of
rock is added to each block, which increased the cost per block by 70 cents.
The cost outlay for block production as of November '96 was $25.70, or approximately $26.00 per
block. Labor for block production is offset by the labor saved for hauling time
to landfill, the labor that would be used to haul blocks purchased from outside
vendors, and truck rental fees. The difference in cost between our
"Bob-Blocks" and those locally available from private manufacturers
is approximately $8.00 per block, ours being the more expensive. The tipping
fee at the landfill for the waste put into one block is $60.00, and would have
been $15,580.50 for the 390 tons we have already disposed of. (For under $8,500, $2,000 of which is one-time
outlay for equipment.)
One hundred fifty blocks
were used on one bank stabilization project by the Surface and Stormwater team.
The Berger Street Detention Pond had one to one slopes on the sides of the pond
in sandy material, which had become increasingly difficult to hold in place.
The concrete blocks were placed on two sides in a three tiered wall, which
produced a stable, attractive, no maintenance bank control. Another 50 blocks
have been utilized by the Road Department for
614 Division Street, MS-26,
Port Orchard, WA 98366 (360) 876-7124
A cooperative effort by Kitap County Departments of Public Works and
Community Development, Bremerton-Kitsap County Health District and Kitsap
Conservation District
various construction
projects, and they have recently ordered more. Some remain in stock at this
time.
Interest in using more of
our "Bob-Blocks" from the Road Department has been strong, and the
Surface and Storinwater Management Program intends to utilize them yearly for
various bank stabilization and erosion control projects. As of June 1997 the
Kitsap County Road Department continues to use our blocks on their bank
stabilization tasks. Our department drew the attention of the Kitsap County
Board of Commissioners last year ('95) and was issued a Waste Prevention Award
for our progress in reducing wastes sent to the landfill.
Latex paint from the 1995
Household Hazardous Waste Round-up has been added to the concrete mixture with
satisfactory results. The latex does not change the color of the block, and
does not noticeably affect strength. This will eliminate another disposal
expense to Kitsap County, and further reduces the volume of waste sent to the
landfill. Many blocks that have had the latex added to them are doing well in
service around the county.
In
conclusion:
The block manufacturing test has proven itself to be cost effective,
environmentally sound and very productive.
Bob Mills
SSWM Operations & Maintenance Supervisor
Kitsap County Public Works
4117 Kitsap Way
Bremerton, WA 98312
(360) 895-8990 or 8996
Appendix E
General Kinematics Drawing of Prototype Street
Solids Separation Equipment
Appendix F
Schematic Drawing of Prototype Street Solids
Separation Equipment